How to sync Story point estimates?

 
2
1
0
I know it is possible to sync the custom field "Story points" but for a jira cloud to another jira cloud cross-company. I cant see any way to sync the "Story point estimate" field. I've tried with: instance_1.issue.customFields."Story point estimate".value = instance_2.issue.customFields."Story point estimate".value But that doesnt sync anything.
    CommentAdd your comment...

    1 answer

    1.  
      1
      0
      -1

      Hi NJ,

      Story points should use time tracking fields such as "Remaining estimate or Time spent". So here is the documentation for this: https://docs.idalko.com/exalate/x/8QB1Aw

      If you have visual, have you tried doing the following:

      jira_cloud_instance_1.issue.timeSpent = jira_cloud_instance_2.issue.timeSpent
      jira_cloud_instance_1.issue.remainingEstimate = jira_cloud_instance_2.issue.remainingEstimate

      Kind regards,

      Ariel