My requirement  is to maintain hierarchy from Project A to Project B


I have project A in which i have version , epic , story

      - In Specific version - i have number of story ,

      - In Specific Epic - i have number story

      - in  Specific story i have number of sub task 


So in similar way i want to sync the Project A with Project B in Jira


(Right now Project B is blank)


----------------------------------------------------------

What i did is like , I used the trigger  and tried to bulk exalate . So in this case all issue reflected to Project B .

But hierarchy is not maintained . So what shoul i do it maintain it .


Ans also what if i sync versions from  Jira project A to Project B  ?? it will automatically sycn Story , sub task . which are internally linked in project A   ????


    CommentAdd your comment...

    1 answer

    1.  
      1
      0
      -1

      The approach is first to ensure that a single hierarchy is syncing correctly.
      Did you had a look at documentation on the topic?
      Syncing agile boards in Jira Server


      Is it helping?