1
0
-1

Hi all,

Is there a way to sync the sprint value of an issue in a case the local sprint and the corresponding remote sprint were already created (but not using Exalate)? I mean - two different users in the two jira's created a sprint, and it has the same name, dates and so on..


Thanks.

  1. Ariel Aguilar

    Hi Yaakov,

    Yes you can check how to sync sprints for Jira On-Premise here:

    https://docs.idalko.com/exalate/x/rgF1Aw

    Most likely, if you implement the sprint mapping correctly, that should be enough and should also work.

    Kind regards,

    Ariel

  2. Yaakov Shamii

    Hi Ariel,

    I'm aware of the document you sent, but in my case it will create duplicate sprints..

    How can I prevent that from happening?

    Thanks

  3. Ariel Aguilar

    Hi Yaakov,

    Then you can delete the duplicate sprint, since there is no way to connect existing sprints into synchronization in Jira Server.

    Kind regards,

    Ariel

CommentAdd your comment...